Guardian iT is being forced to build its own power station to provide power for its latest server farm.
Published: 7 December 2000 17:45 GMT
The gas-fired plant, near Heathrow airport, is needed because Scottish and Southern Electricity were not able to provide sufficient power in time. It would take 18 months for the company to sort out planning permission for pylons and lay cables.
Gary Growns, MD and project leader for Guardian iT, said: "Our site is the largest around and in the timeframe we've got, with the electricity distribution rate we need for our expanding internal companies, we'd either have to delay entry into the market, or move premises. Both are unacceptable to us, so we will build our own plant."
Experience in the electricity arena is highly desirable where strong financial/risk/quantitative skills would be useful. Huxley Associates are ...
The role will involve providing proactive support of SAP Plant Maintenance (PM) and Mobile Asset Management to the IT department and business. A well ...
Top Flight Hedge Fund is looking to hire an outstanding entry level Windows Infrastructure Engineer to join the Systems group, which is responsible ...
CIO50 2008
The silicon.com CIO50 2008 profiles the most influential and innovative tech chiefs in the UK across all industries and organisation size, from the biggest FTSE100 companies to high growth dot-com start ups and the public sector. The list was voted on by the UK CIO community and a panel of experts. Find out more in our latest special report.
Stories from the web...
Copyright ©1995-2008 CNET Networks, Inc. All rights reserved. Top of page
silicon.com Dear silicon.com... ZX Spectrum nostalgia, Mac attack, tag a bag… Reader Comments of the Week
Steve Ranger Editor's Blog: Home computing from Acorn, Amiga and Amstrad, to the ZX Spectrum Nostalgia 2.0...