Leaky pipes cause more delays to Large Hadron Collider's restart

Vacuum conCerns

Tags: cern, lhc

By Tom Espiner

Published: 22 July 2009 08:24 GMT

The restart of the Large Hadron Collider has been pushed back further, following the discovery of vacuum leaks in two sectors of the experiment.

The world's largest particle collider is now unlikely to restart before mid-November, according to a Cern press statement. The project had been expected to start again in October.

To repair the leaks, which are from the helium circuit into the insulating vacuum, sectors 8-1 and 2-3 will have to be warmed from 80K to room temperature. Adjacent sub-sectors will act as 'floats', while the remainder of the surrounding sectors will be kept at 80K, Cern said in the statement. The repair work will not have an impact on the vacuum in the beam pipe.

The LHC experiment, which is designed to answer fundamental questions about the nature of matter, had to be halted nine days after it became fully operational last September, due to a leak of liquid helium. To be super-conductive, the experiment is cooled using liquid helium.

Cern has pushed back the restart a number of times, as repair work has continued. To begin with, scientists said the LHC experiment would restart in April 2009.

In May, Cern told silicon.com sister site ZDNet UK that the restarted experiment could run through the winter to make up some of the lost time. Normally, running the experiments through the alpine winter is prohibitively expensive, due to high electricity costs. However, as the experiment has not been running since last September, Cern would have the budget to cover energy costs over the winter.

Original article: Vacuum leaks lead to more Hadron Collider delays from ZDNet UK

  1. Zones
  2. Management
  3. Networks
  4. Software
  5. IT Services
  6. Hardware
  1. Verticals
  2. Public Sector
  3. Financial Services
  4. Retail & Leisure

Bethan Jones Can I use a netbook as my everyday work machine? Part II silicon.com sub editor reveals whether her netbook delivered

Seb Janacek Magic Mouse - Apple's best ever? Minority Report: After years of disappointment, one Mac lover has hope


  • Jobs
Sales Director

Ambitious in nature you will relish the opportunity to grow a business around you and provide leadership, direction and vision. The European Sales ...

Senior Embedded Software Applications Engineer, West Midlands, Competitive, C, Embedded microcontrollers, product consultancy

Authoring of specifications, test documents and verification plans - Hardware and software partitioning - System and software architecture & design - ...

Senior Project Manager - Kano Nigeria

The team would act as Client? Reporting to the Operations Director, the successful candidate will be responsible for the efficient overall management ...

Agenda Setters 2009
Welcome to the ninth annual Agenda Setters poll – silicon.com's list of the top 50 most influential individuals in the technology and IT industries, from techies and CIOs to entrepreneurs and business leaders. Find out more in our latest special report.





Quick Sitemap Links: